America’s appetite for electricity is growing again. After years of relatively flat demand, new loads are arriving from electric vehicles, electrified heavy industry and, above all, the data centers powering the boom in artificial intelligence. Generating more power is only half the challenge. The electricity also has to get from where it is made to where it is needed, and the high-voltage lines that carry it are not keeping up.

In a Policy Forum paper in Science titled “Fixing the power transmission crisis,” Madeline Yozwiak and M. Granger Morgan of Carnegie Mellon University and David G. Victor of the University of California San Diego argue that the United States faces an extreme transmission shortfall, and that its roots are political rather than technical.

“The fundamental challenge isn’t technical, it’s jurisdictional,” the authors write.

Building a Tenth of What Is Needed

The numbers frame the problem starkly. Over the past five years, the continental United States has built roughly 500 miles of new high-voltage transmission lines per year. Studies cited by the authors call for about 5,000 miles per year in order to triple the capacity of the interregional grid by 2050. At the current pace, the country is building only about 10 percent of what is needed.

Interregional lines matter because they let regions share power. They can move wind energy from the plains to cities, carry solar power across time zones, and help one region recover when another is hit by extreme heat, cold or storms. Without them, new generation can sit idle for lack of a way to reach customers, and grid reliability suffers when demand spikes.

Everyone Can Say No

Why is so little being built? The authors point to how authority over the grid is spread out. “Authority is divided among federal, state, and private entities, each with distinct priorities,” they write.

A long-distance line may cross several states, dozens of counties and the territories of multiple utilities, each with its own approval process and interests. Local communities may object to lines that pass through but bring them little direct benefit. Incumbent utilities, the authors note, may resist regional connections that would weaken their local market power.

The result is gridlock. “When every stakeholder possesses the power to say no,” the authors write, “even high-value projects that benefit the entire nation struggle to move forward.”

A Three-Part Plan

The authors propose three steps to break the logjam.

First, use the authority and technology that already exist. The Federal Energy Regulatory Commission and the Department of Energy have statutory powers to designate national-interest transmission corridors, which the authors urge them to use. On the technical side, they point to reconductoring, replacing the wires on existing towers with advanced conductors, and to newer voltage-source-converter high-voltage direct current (VSC-HVDC) lines, which together could double or triple capacity. Burying HVDC cables along existing highway and railroad rights-of-way could sidestep many of the siting fights that stall overhead lines.

Second, learn from other countries. The United States lags its peers in long-distance HVDC and cross-border planning, the authors say. They suggest a cross-national forum, possibly led by the National Association of Regulatory Utility Commissioners (NARUC), to study and adapt strategies that have worked elsewhere.

Third, create a Presidential-Congressional Transmission Commission. Modeled on past bipartisan task forces, it would recommend legislation, evaluate whether to expand FERC’s authority over siting, and design financial incentives for the developers who build first and for the communities that host new lines.

The Cost of the Status Quo

The authors conclude that the current patchwork approach will fail, with consequences for both the economy and the reliability of the grid. As demand rises, a constrained network can mean higher prices, delays in connecting new power plants and data centers, and greater vulnerability to blackouts during extreme weather.

Policy Forum papers are arguments, not experiments, and the proposals here would face their own obstacles. Expanding federal siting power is politically contentious, especially among states that guard their authority over land use. Buried HVDC and advanced conductors cost money, and incentives for host communities would need funding. The release also does not detail which studies produced the 5,000-mile target.

Still, the core diagnosis is hard to dismiss. The technology to move far more power already exists. What the country lacks, the authors argue, is a way to decide, at the scale of the nation, where the wires should go.

Featured image: High-voltage power lines. Scientific Inquirer media library.


Endnotes

  1. Yozwiak, M., Victor, D. G., and Morgan, M. G. “Fixing the power transmission crisis.” Science (Policy Forum), 12 November 2026.
  2. Carnegie Mellon University College of Engineering. “US facing extreme power transmission crisis, experts warn in Science.” EurekAlert!, 12 November 2026. https://www.eurekalert.org/news-releases/1151552